PRP

Grace period clause and delay interest

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

Many agreements give the builder a grace period, and Authorities generally allow it where it is clearly written and unconditional. Interest then runs from the end of the grace period. A grace period tied to conditions the builder did not meet may not be allowed.

Provisions and law

Sec 18(1), RERA Act 2016; Sec 2(za), RERA Act 2016

Analysis

If possession was due on 30 June 2024 with a six month grace period, interest may start from 1 January 2025. On ₹60,00,000 paid at about 10.85% a year, six months less interest is roughly ₹3,25,000. Read the clause: if it says grace only for force majeure, the builder must prove such events. Claim from the original date and let the Authority decide.

Conclusion

  1. Read the possession and grace clauses together.
  2. Note any conditions attached to the grace period.
  3. Compute interest both ways.
  4. Claim from the earliest date the facts support.

Check your state's model agreement, as it may limit grace clauses.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.