Delay interest is paid on the amount you have paid to the builder, for each month from the agreed possession date until valid possession. The rate is set by the state RERA rules; Maharashtra and the rules followed in Delhi use the SBI highest marginal cost of lending rate (MCLR) plus 2%. Check the latest notification for your state.

Provisions and law

Sec 18(1), RERA Act 2016; Sec 2(za), RERA Act 2016

Analysis

Take the total amount paid, apply the prescribed annual rate and divide by twelve for each month of delay. Example: you paid ₹50,00,000, the possession date was 31 March 2025 and the rate is taken as 10.85% a year (MCLR plus 2%, check the current SBI figure). Monthly interest is about ₹45,208, so 12 months of delay comes to about ₹5,42,500. Payments made after the possession date earn interest only from the date they were paid.

Conclusion

  1. Collect the SBI highest MCLR applicable on the date of the order or as your state rule specifies.
  2. Build a month by month table of amount paid and months of delay.
  3. Attach the interest table to the complaint as an annexure.
  4. Ask in the relief for future monthly interest until valid possession with occupancy certificate.

Do not use the bank FD rate or a rate from a news article; the Authority applies only the rate in the state rules.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.