Facts
An extension of the project registration under Sec 6 extends the promoter's registration, not your agreement. Delay interest under Sec 18 is linked to the possession date in your agreement for sale.
PRP
Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.
An extension of the project registration under Sec 6 extends the promoter's registration, not your agreement. Delay interest under Sec 18 is linked to the possession date in your agreement for sale.
Sec 6, RERA Act 2016; Sec 18(1), RERA Act 2016
Buyers often see a later date on the RERA project page and think their claim has gone. Your agreement date still governs when interest starts, though the builder may argue force majeure for some months. For example, if your agreement says June 2024 and the registration was extended to June 2026, you can still claim interest from July 2024, and the Authority decides any force majeure period it accepts. Keep a copy of the original registration page and the extension order.
Do not sign a new addendum accepting the later date without advice; it may be used to argue you agreed to it.
Connect now
A Savvy replies in minutes.
Fixed price before you pay. Your Savvy is paid only after you accept the work.
General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.