End date for RERA delay interest

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

RERA interest for delay runs till the handing over of possession. Authorities usually take the date of a valid possession offer made after the occupancy certificate, plus the two-month window.

Provisions and law

Sec 18, Real Estate (Regulation and Development) Act 2016; Sec 19(10), Real Estate (Regulation and Development) Act 2016; Model agreement for sale under the state RERA rules (Delhi RERA format)

Analysis

An offer of possession without OC is usually not valid, so interest continues. If OC came in March and a valid offer was made in April, interest generally stops at the offer date, or up to two months later depending on the order. If you take keys later by choice, interest does not run for that extra time. Check your state Authority's past orders.

Conclusion

  1. Note the OC date and possession offer date.
  2. Check whether the offer was valid with OC.
  3. Compute interest up to the valid offer date.
  4. Explain any gap caused by the builder.
  5. Claim accordingly in the complaint.

Delaying taking keys after a valid offer does not extend interest.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.