Builder pleads force majeure or COVID for the delay

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

The Act defines force majeure narrowly: war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the project. Authorities have granted limited time relief for the COVID period in some states, but they do not wipe out the whole delay. Check the latest notification or order of your state RERA.

Provisions and law

Sec 6, RERA Act 2016; Sec 18(1), RERA Act 2016

Analysis

Ask what period the builder is claiming and why. Labour shortage, funding problems or approval delays are not in the statutory list. If the state RERA allowed, say, a six month COVID relief for projects due in 2020, a project due in 2019 or 2022 may not gain the full benefit. The Authority looks at the facts of each project.

Conclusion

  1. Ask the builder in writing for the exact force majeure period and the event claimed.
  2. Check your state RERA orders or notifications on any COVID extension.
  3. In your reply, show the delay before and after the claimed period.
  4. Ask for interest for all months not covered by any accepted relief.

Do not accept a blanket force majeure letter; it must be backed by a recognised event and dates.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.