PRP

Trying settlement before a full RERA case

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

MahaRERA runs a conciliation forum where both sides can settle with the help of a conciliator, and the matter can also be sent there at the first hearing if both agree. Other states do not all have such a forum, so a written demand and negotiation come first. Check the latest notification for the conciliation fee.

Provisions and law

Sec 32(g), RERA Act 2016; Sec 31, RERA Act 2016

Analysis

Conciliation suits short delays where you want possession plus a fair interest credit, not a long fight. Send a written demand with your interest calculation; many builders offer a credit note against final dues. If both agree in MahaRERA, the settlement is recorded and can be enforced. If talks fail, you still file the complaint.

Conclusion

  1. Send a written demand to the builder with your interest working.
  2. In Maharashtra, apply to the conciliation forum or opt for it at registration.
  3. Record any settlement in writing with dates and amounts.
  4. File a RERA complaint if the builder does not settle or does not honour it.

An oral promise of a discount at possession is not a settlement; get it in writing.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.