PRP

OC received but allottee delays taking possession

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

An allottee must take physical possession within two months of the occupancy certificate. After that, delay interest usually stops and the builder may claim maintenance as per the agreement.

Provisions and law

Sec 19(10), Real Estate (Regulation and Development) Act 2016; Sec 18, Real Estate (Regulation and Development) Act 2016; Model agreement for sale under the state RERA rules (Delhi RERA format)

Analysis

Defects are not a reason to refuse possession indefinitely; the better route is to take possession, record defects in writing and claim rectification within the defect liability period. If you refuse, delay interest may run only up to the offer date plus two months. List the defects with photos at handover. Pay maintenance from the date you are liable as per the agreement.

Conclusion

  1. Inspect and list defects in writing with photos.
  2. Take possession within two months of the OC offer.
  3. Send the defect list to the builder for rectification.
  4. Raise unresolved defects with the Authority.
  5. Pay maintenance from the date due.

Refusing possession can reduce your delay interest claim.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.