PRP

Builder asks for no-claim letter at possession

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

Builders sometimes make possession conditional on a waiver of delay claims. Courts and RERA authorities have often refused to hold allottees to such waivers signed under pressure, but it is better not to sign one.

Provisions and law

Sec 18, Real Estate (Regulation and Development) Act 2016; Sec 19(10), Real Estate (Regulation and Development) Act 2016; Sec 31, Real Estate (Regulation and Development) Act 2016

Analysis

If you must sign to get keys, add 'under protest and without prejudice to my rights under RERA' and send a separate email the same day saying so. Keep proof that possession was refused without the waiver. This preserves your claim for delay interest. Never sign a receipt saying all dues settled unless they are.

Conclusion

  1. Ask for possession without the waiver in writing.
  2. If forced, sign under protest with your own note.
  3. Email the builder the same day recording the protest.
  4. Take possession and list defects.
  5. File or continue your delay claim.

A clean waiver signed without protest is the builder's strongest defence.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.