Builder's counter claim for my unpaid dues

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

The allottee is liable to pay interest for delay in payments, at the same rate the promoter pays for its default. Authorities often net off both sides. A demand for a stage not actually reached is not a valid default.

Provisions and law

Sec 19(7), RERA Act 2016; Sec 2(za), RERA Act 2016; Sec 19(6), RERA Act 2016

Analysis

If you paid one ₹5,00,000 instalment four months late, the builder may claim about ₹18,000 interest at 10.85%. If the builder owes you 24 months of delay interest on ₹50,00,000, about ₹10,85,000, the net is still in your favour. Show that late payments were against demands for stages not reached, if true. Ask for netting in the final order.

Conclusion

  1. List your late payments and the demands behind them.
  2. Check if those stages were really reached.
  3. Compute both sides at the same rate.
  4. Ask the Authority to net them off.

Ignoring the builder's claim lets it reduce your award unanswered.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.