LON

Retention money in contractor invoices

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

A factoring unit is for an amount the buyer accepts as payable on a due date. Retention money that is payable only after a defect liability period and conditions is usually not accepted as a current receivable.

Provisions and law

RBI (Trade Receivables Discounting System) Directions, 2026

Analysis

On a Rs 20 lakh bill with 10 percent retention, the buyer will normally accept Rs 18 lakh for payment and keep Rs 2 lakh. You can discount the Rs 18 lakh on TReDS. The Rs 2 lakh can be released later or against a bank guarantee if the contract allows, which your bank can provide. Track retention separately in your books.

Conclusion

  1. Upload the payable part net of retention
  2. Ask the buyer if a bank guarantee can replace retention
  3. Track retention release dates
  4. Claim retention once conditions are met

Uploading retention as if it were due now can be rejected or create disputes.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.