Facts

For micro and small suppliers, the MSMED Act limits the agreed payment period to 45 days from acceptance of goods or services. TReDS does not change that law. A due date beyond 45 days means the buyer is paying late under the Act, even if the invoice is discounted.

Provisions and law

Sec 15 and 16, MSMED Act 2006; RBI (Trade Receivables Discounting System) Directions, 2026, para 18

Analysis

If you discount a 90 day unit, you bear the discount for 90 days, which costs about twice as much as for 45 days. You can ask the buyer to set the due date within 45 days, which also helps the buyer with its tax deduction rule for MSME payments. If the buyer refuses, you still have the right to claim statutory interest for the delay beyond 45 days, through Samadhaan if needed. Weigh this against the relationship.

Conclusion

  1. Show the buyer the MSMED Act 45-day limit and the cost of a 90 day unit
  2. Ask for due dates within 45 days of acceptance
  3. Keep records of acceptance dates
  4. Consider a Samadhaan claim for statutory interest if late payment continues

Medium enterprises are not covered by the 45-day rule, so check your Udyam category first.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.