Facts

GST is charged at the rate on the time of supply, not the contract date. If the contract price is inclusive of GST, the tax part changes with the rate. Sec 171 also pushes you to pass on the benefit.

Provisions and law

Sec 14, CGST Act 2017; Sec 171, CGST Act 2017; Sec 31(5), CGST Act 2017

Analysis

Example: an annual supply contract at Rs 1,18,000 inclusive of 18 percent; if the rate drops to 5 percent, keeping Rs 1,18,000 raises your base price, which looks like profiteering. Amend the contract to show base price plus applicable GST. For services in milestones, the rate depends on each invoice's time of supply. Talk to the customer and document the change.

Conclusion

  1. Read the price clause in the contract.
  2. Split base price and GST for invoices after 22 September.
  3. Issue an addendum showing base price plus GST.
  4. Invoice each milestone at the rate on its time of supply.

Write contracts as base price plus applicable GST to avoid such disputes.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.