Cost overrun funding certificate

Updated . Reviewed by Rishabh Goyal, Chartered Accountant. Every paid answer is checked by a CA. Free AI answers are labelled until a CA verifies them.

Facts

Banks fund cost overruns usually in the same debt-equity ratio, so promoters must bring their share first. A CA certifies the revised cost and the promoter contribution brought in.

Provisions and law

ICAI Guidance Note on Reports or Certificates for Special Purposes (Revised 2016); ICAI Council decision: UDIN mandatory for certificates issued by members

Analysis

If the project cost rises from Rs 10 crore to Rs 12 crore with 70:30 debt-equity, promoters bring Rs 60 lakh. The CA traces that money and certifies cost incurred. Explain why costs rose. Banks may also re-check viability.

Conclusion

  1. Prepare the revised project cost
  2. Bring the promoter share into the business account
  3. Get the CA certificate
  4. Apply for additional loan

Promoter money borrowed back from the company defeats the purpose and is a red flag.

Connect now

A Savvy replies in minutes.

Fixed price before you pay. Your Savvy is paid only after you accept the work.

General guidance from TaxSavvy’s library of money processes. Laws change; your Savvy confirms the answer on your exact case before anything is filed.